Alaska Energy Shenanigans: Eklutna Dam and the RPS (Part I: Background)
Ed. note: Alaskans are waking up to a sneak attack on electric affordability and reliability by agenda-driven special interests and their pliable politicians. The latest concerns the state’s third largest hydro project that has become a Trojan Horse for Green New Deal programs. “Cronyism, abuse and manipulation of our critical energy infrastructure is the result of ‘stakeholder inclusion’,” as energy expert Kassie Andrews writes in this two-part post.
At 40 MW capacity, the Eklutna Hydro Dam Project generates 5–6 percent of the total electricity for the Railbelt. Eklutna provides the most significant share of renewable energy, 44 percent of Matanuska Electric Association (MEA)’s renewable portfolio and 25 percent of Anchorage area-service-provider Chugach’s renewable portfolio.
With capital depreciation and small operating costs, Eklutna is the lowest-cost electricity source for Southcentral Alaska. Assuming carbon dioxide is of concern, this project offsets approximately 72,500 metric tons of CO2 annually, equivalent to 16,911 gasoline powered passenger vehicles driven for one year, equating to roughly half of daily commuters on the Glenn Highway.
Chugach’s effective share of Eklutna is 64.3 percent, up to 25.7 megawatts. Allowing for storage of spring and summer runoff, Eklutna Hydro acts as a pseudo storage battery for power generation and provides on demand firm spinning reserve capacity. Natural economics, no special government subsidy required.
This was demonstrated in the early 2024 cold snap. During the seven-day coldest duration (January 28–February 3, Anchorage Airport reading), the average capacity factor of Eklutna was 77 percent. Compare this to 17.6 MW Fire Island Wind at an average capacity factor of 20 percent, with 0% on February 1, 2024. For Alaskans, wind and solar is 100% unreliable, when we need it most.
New Hydro Politics
The Upper Eklutna Dam was a Federal Bureau of Reclamation Project, constructed in the 1950s. While the transfer of ownership in Eklutna Hydro to the parties of today became official in 1997, a stipulation of the sale was a congressionally approved Fish and Wildlife Agreement. Think politics, and of the worst kind.
The 1991 Fish and Wildlife Agreement acknowledged that hydroelectric developments may have resulted in a “yet to be quantified impact to fish and wildlife resources.” Since the project was not subject to FERC licensing, there “is no opportunity to determine the extent of that fish and wildlife impact.”
The Project Owners, the Municipality of Anchorage, Chugach Electric Association, and Matanuska Electric Association were required to examine and quantify “if possible” the impacts to fish and wildlife from the Eklutna Project. They were to develop proposals for the protection, mitigation and enhancement of fish and wildlife affected by hydroelectric development.
The Municipality of Anchorage lost voting rights on the Eklutna Hydro Electric Project and, subsequently, the 1991 Fish and Wildlife Agreement, when Chugach acquired Municipal Light & Power in 2020.
The timeline set forth in the agreement required the owners to initiate the study process “no later than 25 years after the transaction date,” this process began in 2019, three years early. A final fish and wildlife plan was due to the Governor at least three years prior to implementation in 2027. The final proposed plan was submitted in April of 2024.
New Proposed Agreement
The agreement gave the power to the Governor to issue the final program and remediation plan. The agreement stipulates that the Governor must give equal consideration to the following:
- the purposes of efficient and economical power production
- energy conservation
- the protection, mitigation of damage to, and enhancement of fish and wildlife
- the protection of recreation opportunities,
- municipal water supplies
- the preservation of other aspects of environmental quality
- other beneficial public uses
- requirements of State law
A critical aspect to major projects is stakeholder engagement. Deciding who becomes part of your project, or in this case who should not be involved can make or break the budget, schedule and can negatively affect the outcomes of the project. A grand misstep in the process was the expansion of the consultation process to include “not only the parties to the 1991 Agreement, but also the Native Village of Eklutna (NVE), Eklutna, Inc., The Conservation Fund, Trout Unlimited, Alaska Pacific University, and several other stakeholders interested in the project.”
A New Narrative
Even before the study process began, a narrative was built around the idea that damages to be mitigated included bringing back a sockeye salmon run that existed prior to the placement of the original dam that was constructed in 1929. That dam, the Lower Eklutna River Dam, was removed in 2018 with primary support and funding of the “stakeholder” Conservation Fund, headed by Brad Meiklejohn, who has written extensively in support of degrowth and overpopulation, shamelessly admitting he is in favor of “rapidly downsizing” the United States population to “one hundred million Americans.” And in a statement that should disqualify citizenship, “The last thing the world needs is more Americans, but the second to last thing the world needs is more people.”
While the removal of the Lower Eklutna River Dam helped to solidify the standing of The Conservation Fund as a stakeholder to the future of Eklutna, it did not restore the water to the full length of the river.
The Native Village of Eklutna (NVE) on the remaining Upper Eklutna Dam states
no water spills over the Eklutna Lake Dam down the river except during floods. A 4.5-mile bypass tunnel diverts water from the lake to the power plant. Of the water diverted, 90 percent is diverted to the Knik River for hydropower, while 10 percent is diverted for Anchorage drinking and wastewater, effectively blocking the remaining 14 miles of Eklutna River from its water source.
A portion of the Eklutna River has been left dry, therefore affecting fish runs.
Getting Fishy
In the Supporting Information Document of the Proposed Final Plan, the Project Owners highlight statements regarding fish made by NVE through Traditional Ecological Knowledge (TEK). The document states: “The Traditional Ecological Knowledge (TEK) from NVE indicates that there was a sockeye salmon run in Eklutna Lake before the lower dam was constructed in 1929.”
However, in a 2011 report, the U.S. Army Corps of Engineers (USACE) stated
It is doubtful that significant numbers of sockeye salmon ever spawned in the Eklutna River drainage because suitable spawning area upstream of the lake is limited and water quality in the lake would likely have limited opportunities for spawning in the littoral zone of the lake. Fully 80 percent of the water entering Eklutna Lake comes from two glacial streams that would not be conducive to the consistent survival of sockeye salmon from egg to fry, and the remaining spawning area would not be sufficient to support large numbers of spawning anadromous salmon. In addition, the physical limnology studies of Eklutna Lake suggest that the turbidity in Eklutna Lake during much of the year is not conducive to significant primary production.
And
A separate study was conducted by Loso et al. to try to determine “whether there was an anadromous salmon run into Eklutna Lake prior to 1929” by using marine derived nutrients (MDN) as a biochemical marker in lake sediment. The study found that there was no significant difference in the composition of sediment layers from before and after 1929. However, a sensitivity test was conducted to assess the possibility that a small salmon run may have gone undetected by the isotopic analysis. It was determined that “a salmon run of up to 1,000 per year, and potentially as many as 15,000 per year, would be possible without noticeably altering the measured isotopic composition of the sediments in Eklutna Lake.” Therefore, the results “provide no evidence that such runs occurred, but do not preclude the possible existence of a relatively small sockeye fishery in Eklutna Lake before 1929.
Experts are telling us the lake doesn’t support fish because it doesn’t generate food. There is, however, an abundant, albeit stocked, source of fish at Eklutna Trailrace exists for all Alaskans, with a 2019 stocking plan stating objectives of an 7,500 return of coho and 4,000 return of chinook salmon.
The draft plan, published in October of 2023, outlined the preferred option being to return water flow to 11 of 12 miles of the Eklutna River. This came with a price tag of $57M, with the study alone costing the project owners $8M through November 2023.
Evolution of Plan
After the draft plan was published in October of 2023, the screams by environmental activist stakeholders and the Native Village of Eklutna became louder. In response to the plan, NVE wrote a letter to the Anchorage Assembly on November 10, 2023. This letter highlighted NVE’s disapproval with the draft plan where they unveiled their wishes for the fate of the dam – “We propose simply removing the Eklutna Lake dam within the next decade when sufficient renewable generation capacity exists to replace any power production capacity lost at Eklutna.”
According to NVE, the only viable solution was to remove the Eklutna Dam, along with the clean, reliable and affordable power and water to 90 percent of Anchorage residents it provides only to be replaced with other nonexistent sources – most likely not inexpensive, firm and reliable. In closing, NVE stated:
We are committed to the expansion of renewable energy in Southcentral Alaska, and we are eager to work with all parties towards that goal. Recent projections are that Alaska will easily meet the 80% renewable portfolio standard by 2040 given the known opportunities that include a major expansion of the Bradley Lake hydro that will generate more power than the Eklutna project, and an estimated 200 MW of new wind and solar projects under consideration across the Railbelt.
In a December 4, 2023, letter to the consultant overseeing the draft fish and wildlife plan, NVE slammed the Project Owners for excluding dam removal as an alternative, calling it an “egregious error” in the environmental analysis. According to NVE, “Dam removal is a reasonable alternative because it would provide the most protection, mitigation, and enhancement of fish and wildlife at a cost far lower than the alternatives considered.”
In an attempt to validate the idea of removing the dam, NVE cited a technical report done in 2011 by the US Army Corps of Engineers –
In 2011, the U.S. Army Corps of Engineers (“USACE”) proclaimed that “[t]rue restoration of the Eklutna River ecosystem would require removal of both dams […].”
However, NVE failed to include the rest of the sentence in the report –
at a cost estimated to be well beyond the funding limits on the 206 authority, and that would leave the majority of the Municipality of Anchorage without a water and electrical power supply.
NVE states in closing: “As such, we request that the Project Owners consider our proposed dam alternative to comply with the Agreement’s purposes and provide a myriad of public interest benefits, including the long-term benefit of affordable energy from truly renewable sources.”
Environmentalists Against Hydro
The environmental stakeholders who have weaseled their way into the process are waging a full-on frontal assault against hydropower, aiming to convince people that it is not “green” and that we need to replace our firm and already paid for infrastructure with an extremely expensive and environmentally destructive building block to facilitate Green New Deal profiteering. In the twisted view of depopulationist Brad Meiklejohn: “You can’t really call Eklutna hydropower a renewable resource if you are killing off Alaska’s ultimate renewable resource, salmon.” Those salmon not being for human consumption, apparently.
————–
Part II tomorrow will examine the proposed solutions, past and present, to reveal major questionable ulterior motives from stakeholders and elected officials.
The post Alaska Energy Shenanigans: Eklutna Dam and the RPS (Part I: Background) appeared first on Master Resource.
Source: https://www.masterresource.org/alaska-policy/alaska-shenanigans-eklutna-dam-i/
Anyone can join.
Anyone can contribute.
Anyone can become informed about their world.
"United We Stand" Click Here To Create Your Personal Citizen Journalist Account Today, Be Sure To Invite Your Friends.
Before It’s News® is a community of individuals who report on what’s going on around them, from all around the world. Anyone can join. Anyone can contribute. Anyone can become informed about their world. "United We Stand" Click Here To Create Your Personal Citizen Journalist Account Today, Be Sure To Invite Your Friends.
LION'S MANE PRODUCT
Try Our Lion’s Mane WHOLE MIND Nootropic Blend 60 Capsules
Mushrooms are having a moment. One fabulous fungus in particular, lion’s mane, may help improve memory, depression and anxiety symptoms. They are also an excellent source of nutrients that show promise as a therapy for dementia, and other neurodegenerative diseases. If you’re living with anxiety or depression, you may be curious about all the therapy options out there — including the natural ones.Our Lion’s Mane WHOLE MIND Nootropic Blend has been formulated to utilize the potency of Lion’s mane but also include the benefits of four other Highly Beneficial Mushrooms. Synergistically, they work together to Build your health through improving cognitive function and immunity regardless of your age. Our Nootropic not only improves your Cognitive Function and Activates your Immune System, but it benefits growth of Essential Gut Flora, further enhancing your Vitality.
Our Formula includes: Lion’s Mane Mushrooms which Increase Brain Power through nerve growth, lessen anxiety, reduce depression, and improve concentration. Its an excellent adaptogen, promotes sleep and improves immunity. Shiitake Mushrooms which Fight cancer cells and infectious disease, boost the immune system, promotes brain function, and serves as a source of B vitamins. Maitake Mushrooms which regulate blood sugar levels of diabetics, reduce hypertension and boosts the immune system. Reishi Mushrooms which Fight inflammation, liver disease, fatigue, tumor growth and cancer. They Improve skin disorders and soothes digestive problems, stomach ulcers and leaky gut syndrome. Chaga Mushrooms which have anti-aging effects, boost immune function, improve stamina and athletic performance, even act as a natural aphrodisiac, fighting diabetes and improving liver function. Try Our Lion’s Mane WHOLE MIND Nootropic Blend 60 Capsules Today. Be 100% Satisfied or Receive a Full Money Back Guarantee. Order Yours Today by Following This Link.